How Much Space Does a 16 MW NVIDIA Vera Rubin Data Center Really Need?
From a 16 MW feed to 48 racks, the new CDU ratio, and why forklift access adds 45% to the white space.

Pictured above: Ofer Cohen, founder of B.A.T, next to the NVIDIA Vera Rubin Ultra NVL576 rack.

AI Data Center Design  ·  8 min read

NVIDIA Vera Rubin racks draw up to 230 kW, weigh close to two tonnes and arrive fully populated. Planning the white space for them is not a scaled-up GB200 exercise. Here is a real sizing case: one building, a 16 MW utility feed, and the numbers that actually decide the floor plan.

16MW
Utility feed to the building
48
Compute racks at 230 kW
365m²
White space incl. forklift aisles
790m²
Total building, excl. cooling yard

Key takeaways

  • Only about 75% of the utility feed is left for the GPU racks.
  • The rack-to-CDU ratio drops from 10:1 (GB200) to about 5:1 with standard CDUs.
  • Forklift access adds about 45% to the white space. Most early layouts leave it out.
  • A standard forklift does not belong in the data hall. Plan the route for a pallet truck.

01Start from net power, not gross

The most common mistake in early feasibility studies is dividing the utility feed by the rack power. Cooling, pumps, electrical losses and the supporting IT all come first.

Power budgetMW
Total facility feed (gross)16.0
Cooling, pumps and electrical losses (PUE 1.2, warm-water cooling)−2.7
Critical IT load13.3
Networking, storage and management (~8%)−1.1
Net power for compute racks12.2

12.2 MW ÷ 230 kW gives a theoretical maximum of 53 racks. We plan 48 racks, in 6 clusters of 8. That leaves about 10% headroom and avoids a half-built cluster.

Design decision

This budget puts UPS on the critical loads only (network, storage, management), not on the GPUs. That is common practice for AI training. Full UPS on compute costs another 6–8% of the budget: about 44 racks instead of 48, and a much larger electrical room.

02The rack-to-CDU ratio has changed

GenerationkW per rackRacks per CDU
GB200 NVL72, in-row CDU ~1.3 MW~132~10
Vera Rubin, same CDU~230~5
Vera Rubin, CDU 2 MW and above~2308–10

In this layout we placed two CDUs at the end of every row. Each one is sized for the full row (~1.85 MW), so one unit can fail without throttling the GPUs (N+1). It is conservative, but it keeps manifold runs short and the cold aisle clear. Always confirm the ratio against the CDU model you select.

Inside an NVIDIA Vera Rubin NVL72 switch tray with copper cold plates and liquid-cooling lines
Inside a Vera Rubin NVL72 switch tray. Each NVLink switch chip sits under a copper cold plate, and the coolant enters through quick-disconnect couplings at the rear. Even the switch trays are liquid cooled. Photo: B.A.T

03One row, then the whole hall

Each row has 11 positions, using 800 × 1400 mm cabinets:

Row length: 11 × 0.8 m = 8.8 m Forklift2.5 m Forklift2.5 m CDU CDU GPU GPU GPU GPU GPU GPU GPU GPU NET CDU, each sized for the full row (N+1) Compute rack, 230 kW Row network rack Row load: 8 × 230 kW ≈ 1.84 MW
Top view of one row. The CDUs sit at the row end to keep manifold runs short. Total hall width is about 14 m.

Six rows give the 48 compute racks. A core row for storage, core network and management brings the hall to 72 rack positions:

Position typeCount
GPU compute racks48
CDUs (2 per row)12
Row network racks6
Core: storage, core network, management6
Total rack positions72

04The aisles everyone forgets

With standard aisles and 1200 mm-deep racks, the first layout needed about 250 m². That figure is wrong for Vera Rubin. A two-tonne rack has to be driven to its position, and driven out again when it fails.

The access rules we applied

  • Cabinets 800 × 1400 mm. The extra depth adds 1.2 m over six rows.
  • Cold aisles 2.5 m. A forklift can reach every row.
  • Hot aisles 1.5 m. Room to service the manifolds behind deep racks.
  • Main aisle 3.0 m. A 90° turn with a 1.4 m rack needs more than 2.5 m.
  • Side and rear aisles 2.5 m. A full perimeter route, so no rack blocks its neighbour.

The hall comes out at about 14 m × 26 m = 365 m², roughly 45% more than the first layout.

AreaStandard aislesForklift access
White space (72 positions)~250 m²~365 m²
Electrical rooms: transformers, switchboards, UPS~200 m²~200 m²
Pump and manifold room~80 m²~80 m²
NOC, shipping and corridors~120 m²~140 m²
Total building~650 m²~790 m²
Outdoor cooling yard (dry coolers)+ ~350–400 m²
Still need air containment

Even with liquid cooling, 5–7% of the heat goes to the air. In this hall that is roughly 550–770 kW, so aisle containment stays in the design.

05Moving a two-tonne rack

A populated GB200 NVL72 rack weighs about 1.36 t. Vera Rubin racks are expected at around 1.8 t. A standard 2.5 t forklift weighs 4–4.5 t on its own. Together with the rack, that is more than 6 t on the floor.

StageEquipmentFloor load
Loading dock onlyElectric counterbalance forklift, 2.5–3 t~6.3 t
Route to the row endElectric walk-behind pallet truck, 2–2.5 t~2.3–2.5 t
Where lifting is neededWalk-behind stacker, 1.6–2 t~3–3.3 t
Final positionThe rack's own casters1.8 t

06Three checks for every site survey

1

The whole load path. Every metre from the dock to the row (ramps, lifts, raised floor) must be approved for the point load, not just the final position.

2

Clear heights. Doors and openings need at least 2.4 m clear for a ~2.3 m rack on its transport pallet.

3

The delivery method. Ask the integrator whether racks move on their own casters or on a pallet. The answer changes the aisle width you need.

07The bottom line

For a 16 MW Vera Rubin facility, plan for 48 compute racks, about 365 m² of white space and about 790 m² of building, plus an outdoor cooling yard.

The GPU specs do not decide the result. The net power budget, the CDU sizing and the logistics of moving two-tonne racks do. Fixing them at the feasibility stage costs far less than finding them during installation.

These figures are planning-stage estimates based on specifications published at the time of writing. Final values depend on the selected CDU, the cooling design and the site.